The burial depth depends on the desired height of the riser pipe above the finished terrain.
Anchoring
Solid material must be used to secure the well against buoyancy:
Minimum 30 cm stabilizing gravel must be placed on top of and around the base plate.
Minimum 15 cm stabilizing gravel must be used outside the base plate.
For example, if the base plate is 100x100 cm, the stabilizing gravel must fill 30x115x115 cm (HxWxL).
Heavy Traffic
If WaterStation is used in areas with heavy traffic, a concrete ring must be established and finished with a well frame and cover:
The well frame must be placed above the riser pipe.
The concrete ring must be cast around the well frame.
Pedestrian Traffic
If WaterStation is used in green areas or areas with pedestrian traffic, it can be finished with an aluminium cover.
Public revision 21/08/2026
Cookies on Vika Help
Vika Help uses necessary browser storage and, if you allow it, statistics cookies for Google Analytics. You can accept all, reject all, or open settings.
Cookie settings
Choose which categories may be used on Vika Help.
NecessaryAlways on. Required to remember your consent choice and keep the documentation shell working as intended.
Allows Google Analytics to measure aggregate use of the documentation site.