FlexVander Commissioning

Test the installed pump layout, included values, access, and stop path before handover.

Before You Start

Do This

  1. Record the FlexVander model, controller serial number, drawing revision, and selected pump program.
  2. Apply power and confirm that the controller reaches its normal ready state.
  3. Check inactive inputs and outputs before a pump is started.
  4. Start one allowed pump under safe conditions.
  5. Confirm the physical pump, run feedback, FlexVander status, and Emiko status.
  6. Stop the pump and confirm that the physical pump and feedback return to the safe stopped state.
  7. Repeat the start and stop test for every pump allowed by the selected program.
  8. Verify pressure control, meters, field values, and notifications when they are included.
  9. Test the approved local operating method only when it is part of the delivery.
  10. Record the result, changed settings, open defects, and handover owner.

Verify

If It Fails

Return the installation to a safe state. Do not bypass a missing stop, feedback, or pressure condition. Record the exact failed step and observed state.

Next Step

Hand over normal operation, access ownership, maintenance duties, and the first support route.